top of page

​​​

​​03 . 18 . 13 - The designs for the column supports and lateral transfer platforms in

                     each embankment was completed.

03 . 05 . 13 - Received Shear-Moment Diagrams developed by Virtis/Opis for a  

                    continuous span beam. Additionally, column supported embankments

                    (CSE) were selected as the soil improvement to adequately prevent

                    stability failure. The design and layout of these columns was

                    determined.

 

03 . 01 . 13 - Second Meeting with the NJDOT to discuss continuous span bridge

          

                     design. The program Virtis/Opis was used to evaluate the trial beam

 

                     cross section.

02 . 15 . 13 - The trial  beam cross section specifications were updated for analysis

                     in program at NJDOT. Additionally, an embankment stability analysis

                 

                     was completed for both approach embankments. Soil improvements

                     were determined to be necessary to stabilize the structure.  



02 . 08 . 13 - Settlement Analysis of the approach embankments completed. Soil

                     improvements for settlement advancement were deemed not

                     necessary.

 

02 . 01 . 13 - First meeting with NJDOT to discuss continuous span bridge design

                     and information needed to run bridge analysis software.

01 . 22 . 13 - Begin Senior Project II work on bridge project.

 

 

01 . 11 . 13 - Site Visit to Bass River Bridge.

                             The team received a site tour from project engineers at Hardesty

                     & Hanover and Parsons Brinckerhoff. It began with a review of the

                     soil  reinforcements in each of the approach embankments.

                     The group then moved to the bridge structure where the

                     structural design, concrete deck, and adjacent bridge improvements

                     were discussed. Moving to the Northern bank of the Bass River below 

                     the bridge, the scour effects at each pier location was mentioned and

                     the condition of the existing bridge was noted. (See "Photos" for site 

                     tour)

12 . 12 . 12 - Senior Project I Design Report completed



12 . 05 . 12 - Final Senior Project I Design Presentation



11 . 27 . 12 - The geotechnical team determined the  remaining soil strata        

                     properties through Standard Penetration Number (SPT N-value)  

                     correlations.

​11 . 20 . 12 - The structural team completed a wind load analysis and, thus,

                     completed the overall load analysis.

11 . 07 . 12 - Preliminary Design Review Presentation

10 . 24 . 12 - The geotechnical team determined the soil strata properties from the  

                     laboratory data. The structural team completed the shear and  

                     bending moment load analysis for both the dead load and live load.

10 . 23 . 12 - The geotechnical team identified nine soil strata beneath the bridge              

                     of which 3 were cohesive and 6 were granular. 



​10 . 17 . 12 - The structural team developed a trial section for an interior main 

                    

                     span girder. The number of girders and the depth thickness were 



                     also selected.

10 . 10 . 12 - Realistic Constraints and Specifications Presentation by all members

09 . 26 . 12 - Hydraulic Team received purchased Topographic Maps

 

09 . 10 . 12 - Structural Team received AASHTO LRFD Bridge Design Manual

 

09 . 05 . 12 - Project Proposal Presentation given by Nick Izzo

 

09 . 04 . 12 - Acquired data from Hardesty and Hanover through Dr. Krstic

Updates

bottom of page