August 2012
- Begin Senior Project I
September 2012
- Project Proposal Presentation
October 2012
- Realistic Constraints and Specifications Presentation
- Bass River Bridge Site Visit
- Preliminary Design Presentation
November 2012
- Teamwork Assessment
- Safety Form
December 2012
- Final Design Report & Presentation
January 2013
- Begin Senior Project II
April 2013
- Final Design Report and Presentation